Our mission has been to transport a 140 TN transformer from the factory to the electrical substation, placing it in its final position on the bench.
Being a piece with a lot of height, the transport required the use of one of our beam equipment, specifically the 200 tn. of capacity with modular trailers of 4 and 6 axes.
As the internal route was very winding, we had to transfer the load to a combination of our self-propelled trailers, for which we used one of our hydraulic gantries, as can be seen in the following image.
Â
Â
The final journey on our self-propelled trailer had to overcome a demanding slope of 13% and did it without flinching as we can see in the following video.
Â
The hydraulic gantry, which we had previously moved and assembled in the final location, was responsible for performing the download with which we finalized our work.